1

Occupancy activity schedule in Design Builder

How can I enter schedule for occuoancy activity because as far I can see Design Builder do not provide this option?

C:\fakepath\Screenshot_1.jpg

orcunkoral's avatar
31
orcunkoral
asked 2019-04-11 06:01:26 -0500
__AmirRoth__'s avatar
4.4k
__AmirRoth__
updated 2019-04-11 07:31:23 -0500
edit flag offensive 0 remove flag close merge delete

Comments

add a comment see more comments

1 Answer

1

The occupancy schedule is set in the Activity tab. You can either use the default schedule for the activity (such as office) or one of the other pre-defined schedules, or you can create and use your own. All of this is explained in the Program Help and the free online tutorials available via the DesignBuilder website.

Dave's avatar
1.6k
Dave
answered 2019-04-13 04:48:56 -0500
edit flag offensive 0 remove flag delete link

Comments

add a comment see more comments