When I created occupancy and lighting schedules for my project, I entered them in the space data screens, but they are not being used for my compliance analysis. How can I fix this?

NORESCO's avatar
341
NORESCO
asked 2014-11-04 18:40:10 -0500
Neal Kruis's avatar
4.7k
Neal Kruis
updated 2015-01-09 12:02:47 -0500
edit flag offensive 0 remove flag close merge delete

Comments

add a comment see more comments

1 Answer

2

For a compliance analysis, all schedules used are defined by the ACM. Any schedules defined or assigned by the user will be ignored. User schedules will only be used when the software is run in research mode.

cbecc's avatar
286
cbecc
answered 2014-11-05 11:33:19 -0500
edit flag offensive 0 remove flag delete link

Comments

The compliance software includes equipment schedules for Title 24 correct? Are there any schedules that the user is expected to define for Title 24?

macumber's avatar macumber (2014-11-06 09:58:01 -0500) edit

No- there are no schedules that the user is expected to or even allowed to define in the Title 24 performance model.

Anna Osborne Brannon's avatar Anna Osborne Brannon (2015-12-11 18:44:28 -0500) edit