Hi, in OpenStudio I have created my building with 3 zones, 1 of which has computers and elevators. To this zone I have assigned two different ElectricEquipmentLoads, one for the computers (15 W / mq) and one for the elevators (110000 W). I would like to assign two different schedules to these two loads. How can I do it? image description image description image description

Cinzia's avatar
51
Cinzia
asked 2020-09-26 16:16:53 -0500
__AmirRoth__'s avatar
4.4k
__AmirRoth__
updated 2020-09-30 07:52:13 -0500
edit flag offensive 0 remove flag close merge delete

Comments

add a comment see more comments

1 Answer

1

You are almost there. You have assigned a default schedule to be used for plug loads instances for the space type. All you need to do is take schedule to represent the elevator fractional schedule from the "My Model" or "Library" tab and drag and drop that onto the box in the Schedule column at the elevator load instance row (next to the elevator definition). This will override the default schedule.

David Goldwasser's avatar
20.4k
David Goldwasser
answered 2020-09-27 14:08:06 -0500
edit flag offensive 0 remove flag delete link

Comments

Thank you @David Goldwasser!

Cinzia's avatar Cinzia (2020-10-07 14:30:15 -0500) edit
add a comment see more comments