How to set month by month simulation parameters in energyplus

For example, In January month we want to set the occupancy to 100 people while 200 people for February and so on. Some general approach applicable to various other parameters also would help.

santle's avatar
65
santle
asked 2019-08-27 07:55:16 -0500
shorowit's avatar
11.8k
shorowit
updated 2019-08-27 09:58:16 -0500
edit flag offensive 0 remove flag close merge delete

Comments

add a comment see more comments

1 Answer

1

In schedule-compact- month-wise, day-wise, and hour-wise scheduling of people, setpoint temperature and so on can be configured.