First time here? Check our help page!
2

TABLE G3.1.1A Baseline System Selection

Hello,

What is in your opinion the baseline for the following building:

Floor area:10,200 sqm (109,600 sqft) Floors: 5 above grade, mostly conditioned. 2 above ground parking, mostly unconditioned- Floor arrangement (G+Parking+Parking+4).

What should be the system type 6 or system 8 as per TABLE G3.1.1A (based on building heating)?

Thanks,

Javed's avatar
273
Javed
asked 2019-05-02 22:23:10 -0500
__AmirRoth__'s avatar
4.4k
__AmirRoth__
updated 2019-05-03 07:39:00 -0500
edit flag offensive 0 remove flag close merge delete

Comments

1

which code are you using?

Luis Lara's avatar Luis Lara (2019-05-03 11:13:03 -0500) edit
add a comment see more comments

1 Answer

2

Taking into consideration what is said in this discussion I would say you have a Nonresidential with more than 5 floors which falls in system 8 - VAV with PFP Boxes.

Fábio Batista's avatar
209
Fábio Batista
answered 2019-05-03 06:28:21 -0500, updated 2019-05-03 06:28:52 -0500
edit flag offensive 0 remove flag delete link

Comments

add a comment see more comments