people count differences

Hi all, i would like ask someone to help me with this problem. I scheduled 38 persons from 7:30 to 9:00 am, but when I see the results of the zone people count I observed that the result start from 6:31 instead of 7:30 (see images below) and I don't know how this happen. I would like to know what is the reason for this and how can I fix this.

Thank you and your help is much appreciated.

image description image description

Philip Caesar Ebit's avatar
181
Philip Caesar Ebit
asked 2018-11-13 01:50:55 -0500
__AmirRoth__'s avatar
4.4k
__AmirRoth__
updated 2018-11-13 10:17:56 -0500
edit flag offensive 0 remove flag close merge delete

Comments

Are you applying Daylight Savings Time (DST)? This is an input field of the RunPeriod object.

Aaron Boranian's avatar Aaron Boranian (2018-11-13 14:57:48 -0500) edit
add a comment see more comments

1 Answer

3

Fairly certain that @Aaron Boranian has pointed out the reason. EnergyPlus always reports time series output using standard time. When daylight savings time (DST) is active, all scheduled values will shift up an hour.

MJWitte's avatar
9.7k
MJWitte
answered 2018-11-16 16:46:35 -0500
edit flag offensive 0 remove flag delete link