Since Energy-Plus calculates the peak load and displays it using ZoneLoadComponentSummary, it is possible for us to tweak the program a little bit to force monthly load component summary ?

Hi, I know this question is a cliche, but I would like to know if any one has a tweak.

Siv's avatar
653
Siv
asked 2018-07-19 06:04:14 -0500
__AmirRoth__'s avatar
4.4k
__AmirRoth__
updated 2018-07-19 10:05:03 -0500
edit flag offensive 0 remove flag close merge delete

Comments

1

Have you tried running separate simulations for each month?

JasonGlazer's avatar JasonGlazer (2018-07-19 09:47:15 -0500) edit

Cool, it works when I create 12 different design days for 12 months based on ASHRAE climate data and run the simulation 12 times. Its tedious, but works. Thank you for your response.

Siv's avatar Siv (2018-07-20 00:23:45 -0500) edit

I'm going to summarize this as a response.

JasonGlazer's avatar JasonGlazer (2018-07-20 10:23:18 -0500) edit
add a comment see more comments

1 Answer

1

There is no built in way to get the ZoneLoadComponentSummary report for each month.

A work around is to run separate EnergyPlus simulations for each month. To do this, create 12 different design days for each of the 12 months based on ASHRAE climate data. Run the simulation 12 times with each design day, once for each month.

JasonGlazer's avatar
6.8k
JasonGlazer
answered 2018-07-20 10:26:59 -0500