How can I run a simulation for 100 days

Can someone please tell the actual changes to be made in the idf file to simulate a model for x days? Given that the parameters like occupancy count is already available / stochastic-ally generated

cs_bot's avatar
247
cs_bot
asked 2018-02-21 02:21:04 -0500
__AmirRoth__'s avatar
4.4k
__AmirRoth__
updated 2018-02-22 07:17:50 -0500
edit flag offensive 0 remove flag close merge delete

Comments

add a comment see more comments

1 Answer

4

You can change the length of simulation by editing the RunPeriod object. Pretty much the first thing you will see when you open an .idf file. You can edit the start and end day.

josh.sykes's avatar
181
josh.sykes
answered 2018-02-21 04:54:33 -0500
edit flag offensive 0 remove flag delete link