Heating/Cooling Schedule link to Occupany schedule

Hi:)

Anyone knows how to link the heating and cooling schedule to the occupancy hours?

What I want is to turn the heating and cooling on when people are in the place at certain temperature.

Thanks a lot! Leshi

leshiz's avatar
103
leshiz
asked 2016-07-08 03:47:43 -0500
__AmirRoth__'s avatar
4.4k
__AmirRoth__
updated 2016-07-08 10:55:40 -0500
edit flag offensive 0 remove flag close merge delete

Comments

add a comment see more comments

1 Answer

4

There is no way to do this directly in Energy+ without writing a script using EMS (Energy Management System). The easiest way I have found to coordinate schedules is to use excel to create the schedules. In excel, I can coordinate values and use conditional formatting to determine values for each schedule. I then use excel's "concat" function to develop Schedule:Compact objects. The image below shows schedule development for occupancy, lighting/receptacle and HVAC systems. The same could be done with thermostat schedules.

Snapshot of Excel File Showing Schedule Development

kwalkerman's avatar
1.5k
kwalkerman
answered 2016-07-08 08:11:26 -0500
edit flag offensive 0 remove flag delete link